Altru Hospital construction is underway. From now until targeted opening in 2022, there will be ongoing construction activity at the Columbia Road Campus. 

May 6 - 10

Expect heavy truck traffic as excavation soil is hauled away from the site. Entrance and exits from the construction site will be staffed by construction traffic control flaggers. Construction activity is weather-dependent and subject to change based on conditions. All work during bulk excavation will take place 24/6 (Monday through Saturday, 24 hours each day to decrease the duration of this process).

Please call 701.780.5000 or submit a comment, question or suggestion at altru.org/future.