Hospital Construction

Altru Hospital construction is underway. From now until targeted opening in 2022, there will be ongoing construction activity at the Columbia Road Campus. Altru will publish the work expected to occur in the near future. We will also post whenever a construction activity will be especially impactful to neighbors.

Current Construction Update

From June 17-21, construction crews are scheduled to perform the following activities:

  • Piling continues
  • Work will begin on the canopy over the emergency department and the existing above ground link
  • Concrete crews will begin mobilizing to begin work on the concrete structure of the new hospital

Piling begins at 8 a.m. and concludes at dark each day. Construction activity is weather dependent and subject to change based on conditions. Please remember safety is our top priority near the construction site. Please do not walk on roadways.

Please call 701.780.5000 or submit a comment, question or suggestion at altru.org/future.


Previous Updates

June 10-14

From June 10-14, construction crews are scheduled to perform the following activities:

  • Piling continues
  • Trauma elevator shoring nears completion
  • Urgent care and Emergency department canopy and above grad link demolition begins

Piling begins at 8 a.m. and concludes at dark each day. Construction activity is weather dependent and subject to change based on conditions. Please remember safety is our top priority near the construction site. Please do not walk on roadways without sidewalks.

Please call 701.780.5000 or submit a comment, question or suggestion at altru.org/future.

June 3-7

From June 3-7, construction crews are scheduled to perform the following activities:

  • Completing bulk excavation and site utility relocations
  • Continue piling operations
  • Installation of a shoring box to allow excavation of the trauma elevator mat footing

Piling begins at 8 a.m. and concludes at dark each day. Construction activity is weather dependent and subject to change based on conditions
Wednesday, June 5, join Altru for the ceremonial groundbreaking and community and employee celebration beginning at 5 p.m. on the west side of the construction site.

For more details >>

Please call 701.780.5000 or submit a comment, question or suggestion at altru.org/future.

May 27-31

From May 27 - 31, construction crews are scheduled to perform the following activities:

  • Wrapping up bulk excavation on the west side of site
  • Site utility relocations
  • Continue piling operations
  • Installation of shoring box to allow excavation of the trauma elevator mat footing

Piling begins at 8 a.m. and concludes at dark each day. Over 50 piles have been set. Construction activity is weather dependent and subject to change based on conditions.

Please call 701.780.5000 or submit a comment, question or suggestion at altru.org/future.

May 20-24

From May 20 to May 24, construction crews are scheduled to perform the following activities:

  • Continue bulk excavation on west side of site
  • Piling continues on east side of site
  • Installation of storm sewer on west side of site

Piling begins at 8 a.m. and concludes by dark each day.

Please call 701.780.5000 or submit a comment, question or suggestion at altru.org/future.

May 6-10

Altru Hospital construction is underway. From now until targeted opening in 2022, there will be ongoing construction activity at the Columbia Road Campus. Altru will publish the work expected to occur in the near future. We will also post whenever a construction activity will be especially impactful to neighbors.

From May 6 to May 10, construction crews are scheduled to perform the following activities:

  • Bulk excavation for building footprint on the east side of the construction site
  • Tie-in of the new water system
  • Installation of new storm sewer

Expect heavy truck traffic as excavation soil is hauled away from the site. Entrance and exits from the construction site will be staffed by construction traffic control flaggers. Construction activity is weather-dependent and subject to change based on conditions. All work during bulk excavation will take place 24/6 (Monday through Saturday, 24 hours each day to decrease the duration of this process).

See the live construction cam

Please call 701.780.5000 or submit a comment, question or suggestion at altru.org/future.


Construction Schedule

  • Piling - 16 weeks
    • Begins May 13 with completion expected in September
    • Expect elevated noise
  • Concrete Structure
    • Beginning the end of June
  • Steel Superstructure
    • Beginning the end of October

FAQs: Deep Foundation and Piling

What is the loud pounding noise? The noise is the foundation of our new hospital being driven deep into the ground. This process is called piling.

What is piling? Piling is the vertical structural element of a deep foundation, driven or drilled deep into the ground at the building site. The purpose of piling is to support the structure of a building.

When will piling take place and for how long? The piling process is expected to last 16 weeks, beginning during the week of May 13. Over 600 piles, totaling 19 miles of material, will be inserted into the ground as the foundational support for our new hospital.

What hours will piling take place? Piling will begin at 8 a.m. and conclude at dark. Primarily, piling will take place Monday through Friday unless weather or operational delays cause adjustments.

Will piling affect the surrounding buildings? The piling will not affect the structure of the current buildings on our Columbia Road campus or in the neighborhood. Intensive monitoring of vibration is in place to ensure activity is within allowable limits.